Quoted email from Dan Wilcox as follows.
Classification: UNCLASSIFIED
Caveats: NONE
All,
Just wanted to bring everyone up to speed on where we are in the planning
process for the above project.
1. The Preliminary Draft Definite Project Report was received from
HDR on December 4. The report was reviewed in Dec/Jan by a team from outside
the Mississippi Valley Division as required by new Corps guidance. Comments
by this review team have been addressed by HDR and MVP. Most of the comments
made were minor, however, there were a few questions related to Dam Safety
Assurance. Additional comments were also received from Phil Delphey and
Kevin Stauffer.
2. A VE Study (Value Engineering) started yesterday and should be
completed by the end of this week. The VE study will be incorporated into
the report as an appendix. Any cost/schedule saving identified are usually
incorporated/implemented during the plans and specification phase.
3. The next step is to brief Mississippi Valley Division on the
report before it gets released for the 30-day public review period (will
include another public meeting in Red Wing). I don’t see this happening
until February.
4. An additional limited independent external peer review (IEPR)is
also required because of the Dam Safety issue. This will be done concurrent
with the public review. The IEPR will only focus on Dam Safety and when
completed, will be included in the final report.
Please call me directly if you have any additional comments, concerns or
questions.
Tom Novak
Project Manager
U.S. Army Corps of Engineers, St. Paul District
180 5th Street East, Suite 700
St. Paul, MN 55101-1678