We’ve got about 16-17 yards to have poured for our slab.
Question for concrete experts…
I’ve heard from some say people it’s better to wait and let things settle over time before doing concrete work near a build. This 40′ wide spot in front of the garage had 18″ of breaker put down in October and a skim of class 5 with fines as needed this Spring. The tentative plan is to pour at the end of the build in June, then finish the remaining 1100′ of driveway with class 5 on top of the 18″ of breaker. The breaker was run with a road compactor in the fall. I could easily dribble a basketball down it and would break a shovel trying to dig in it.
Would you be comfortable pouring the slab in this area yet this year, or would you go a year longer on the breaker in front of the garage? The original soil in the area was a sandy loam on top of clay. Most of the sandy loam was dug out before the breaker went on, but it’s crazy how much of the breaker has been eaten by the soil.